I need to schedule the following rule :
Process must run each working days of the month, except the 3 first working days of this month.
Is there a simple way to manage this by the rule ?
Because today I notice we can easily exclude the 3 first calendar days of the month with the new tab "Days in Month", but I need the same with Working Days.
By the same way, the task today doesn't allow to exclude non explicit dates.
I know there's some other solution for this (like create a dedicated calendar with 3 first working days off) but I just want if there's a more simple and optimized way to do it
Thanks for advice !