Solved : How to build a rule to run a job the first 5 days of each month?


1 reply to this topic

#1 Chris

    Newbie

  • Members
  • 6 posts

Posted 15 May 2008 - 04:11 PM

Hello,

How can I schedule a job the first 5 days of each month?

#2 men

    Hero Member

  • Root Admin
  • PipPipPipPip
  • 4,389 posts
  • Gender:Male
  • Location:Europe

Posted 16 May 2008 - 10:58 AM

Hello Chris,

you can do the following :

if you are running the V5.3, you need to create 1 Rule with the following characteristics :

Period : 1 Day
Position in period : 1 Calendar Day from Beginning
Offset : None

Days of the week : Check all (all allowed)

Days in month : Check from the 1st to the 5th from beginning

If you are running an earlier version (5.0 to 5.2), you need to create 5 Rules (one for the 1st day of the month, one for the 2nd day of the month, ..., one for the 5th day of the month), with the following characteristics :

Period : 1 Month
Position in period : 1 Calendar Day from Beginning (for the 1st) or 2 Calendar Days from Beginning (for the 2nd) or ... or 5 Calendar Days from Beginning (for the 5th)
Offset : None

Days of the week : Check all (all allowed)

The 5 Rules must be assigned to the Task.


In both cases, the application date of the Rules should be the 1st day of a month.

Michel